II A new application development project at NeuProd, Inc. consists of the following activities? Create a WBS
10 pts. (Extra)

Determine the slacks using critical path technique, draw a basic diagram of how critical path is calculated:

What is the critical path? What is the total slack?
Which activity has the largest slack? Crash the project by three days and re-identify the critical path.